A construction estimate is much more than a final number on a page. It takes a thorough review of project documents, detailed quantity takeoffs, trade pricing and coordination across several departments to develop an accurate picture of what a project will cost. We recently sat down with Peter Quathamer, who runs our estimating department at JCP Construction, and asked him about how construction estimates are built. Here’s what he had to say:

——————————————————————————–

With my estimating experience, I’ve seen how much work goes into building an estimate before a project ever reaches the construction phase. Every project has its own requirements, challenges and considerations.

It Starts with the Project Documents

Before we begin putting numbers together, we read through the project documents carefully. That includes the drawings, specifications and every addendum issued during the bidding process.

In my experience, some of the biggest estimating misses can start here. Overlooking a detail or missing a change in an addendum can affect quantities, scope and ultimately the project cost. Taking the time to understand what the project requires gives us a much stronger starting point.

Building the Takeoff

Once we understand the scope, we begin measuring and quantifying the work. Our team uses Bluebeam to complete digital takeoffs, with quantities organized in our estimating workbook.

Accuracy is important, so we build in another layer of review. Luis Guereca (another estimator on our team) and I check each other’s quantities to help catch discrepancies and make sure the estimate reflects the work shown in the documents.

These quantities become the foundation for pricing the project. The more accurate the takeoff, the more reliable the estimate.

Pricing the Work

Not every part of a project is priced the same way. At JCP Construction, we self-perform concrete and carpentry work, so we use our own crew production rates to determine labor and costs for those scopes.

For other portions of the project, we reach out to subcontractors for pricing. Getting the right coverage is important, and we want enough bidders for each trade to give us a clear understanding of the market and the work involved.

Once bids come in, we level them by comparing each subcontractor’s proposal scope-to-scope. This helps us identify differences, missing items and gaps between trades before they become issues later in the project.

Accounting for Site Conditions and Logistics

A project’s cost involves more than materials and labor. Site conditions, access and construction logistics can all have a significant impact on the estimate.

For example, a tight lot in Milwaukee might require a concrete pump to be set up in the street, along with a city right-of-way permit and traffic control. Those costs need to be accounted for from the beginning.

This is where input from our field leadership is especially valuable. They help us think through how the work will actually happen in the field, identify potential challenges and make sure the estimate accounts for the logistics
involved.

Understanding Budgets, Assumptions and Exclusions

Not every estimate starts with a complete set of construction documents. Many projects begin with an early budget based on preliminary plans and information.

When that happens, it’s important to document the assumptions, clarifications and exclusions behind the number. I want everyone involved to understand what the estimate includes, what it doesn’t and what may still change as the project develops. An early budget is a useful planning tool, but it shouldn’t be mistaken for a final construction price.

The Estimate Doesn’t End at Bid Day

Once a project moves forward, the estimate becomes the foundation for the project budget. Our estimating team walks the project manager and superintendent through the estimate during the handoff, reviewing the scope, pricing and details that went into building it.

This handoff is an important part of the process. The team responsible for building the project needs to understand how the estimate was put together and where specific costs came from.

We also track subcontractor bids and project costs over time. That information helps us build a history of pricing and production rates that we can reference when estimating future projects.

Building a Stronger Foundation for the Project

A good construction estimate takes careful review, detailed pricing and collaboration between the people who understand the plans and the people who will build the project.

For me, the goal is to develop an estimate that gives our team and our clients a realistic understanding of what a project will take. The work that happens during estimating helps set expectations, support better decisions and create a stronger foundation for the construction process.